PHASE 1 REPORT
WORK SUMMARY
Lot 1-
- Parapet wall, block work and plastering completed.
Lot 2-
- Roofing parapet wall block and plastering completed.
Lot 3-
- Parapet block wall 90% done.
Lot 4-
- Parapet block wall 90% done.
Lot 5 (10% to end of milestone 5)-
- The slab casting is 100% done.
- Column boarding and casting 30% done,
Lot 6 (30% to end of milestone 5)-
- Block work completed.
- Column boarding casting 45%
- Slab losing almost completed.
Lot 7 (60% to end of milestone 5)–
- Block work 100% done.
- Column boarding 100% done.
Lot 8-
- Plastering 90% done.
- Parapet wall 70% done.
Lot 11 (60% to end of milestone 4)-
- Slab casting completed.
Lot 13 (90% to end of milestone 5)-
- The block work is 100% done.
- Column casting is 100%. done.
- plumbing work 20%(1 basement flat)
Lot 14 (70% to end of milestone 4)-
- Plumbing and electrical work has been completed for the first two units.
- While the second two unites reinforcement, work completed.
- Electrical work completed.
- Casting in view.
Lot 15 (90% to end of milestone 5)-
- Block work above lintels are 50% done with all columns installed with casting 98% completed.
Lot 16-
- Basement carpeting work ongoing.
FD 1-6 (70% to end of milestone 4)-
- Slab all casted.
FD 7 (50% to end of milestone 7)-
- The carpentry work is done.
- Roof beam ready for casting.
FD 8-
- Parapet wall in progress.
FD 9-
- Parapet wall in progress.
- Screeding (external) 70% done.
FD 10-11 (70% to end of milestone 3)-
- The block to ground floor slab is 100% done.
- Column casting 98% done.
APPENDIX
LOT 11- Slab casting completed.
LOT12- The Block work is 100% done.