PICTORIAL VIEW OF GLENDALE PLUS STATE OF WORK 

BLOCK A 

  • Wall painting (external)                                                              30% 
  • Tyrolean wall finishes                                                                  95% 
  • External wall screeding                                                              100% 
  • Installation of staircase balustrade                                          100% 
  • Plastering of internal wall                                                          100% 
  • Plastering of external wall                                                         100% 
  • Electrical piping on each floor                                                   100% 
  • Electrical wiring on each floor                                                   100% 
  • Plumbing work on each floor                                                    100% 
  • Setting of partition wall                                                              100% 
  • POP ceiling installation                                                               100%
  • Fixing of window                                                                          100%
  • Fixing of window hood and wall belt                                        100% 

BLOCK B 

  • External wall screeding                                                                90% 
  • Plastering of external wall                                                          100% 
  • Plastering of Internal wall                                                          100% 
  • Setting of partition wall                                                              100% 
  • Electrical piping on each floor                                                   100% 
  • Electrical wiring on each floor                                                    80% 
  • Plumbing work on each floor                                                     80% 
  • Setting of partition wall                                                              100% 
  • POP ceiling installation                                                                95% 
  • Fixing of window                                                                          100% 
  • Fixing of window hood and wall belt                                        100% 

BLOCK C 

  • Wall painting (External)                                                               30% 
  • Tyrolean wall finishes                                                                   90% 
  • External wall screeding                                                                 90% 
  • Plastering of Internal wall                                                           100% 
  • Plastering of external wall                                                           100% 
  • Setting of partition wall                                                               100% 
  • Electrical piping on each floor                                                    100% 
  • Electrical wiring on each floor                                                    100% 
  • Plumbing work on each floor                                                     100% 
  • POP ceiling installation                                                                95% 
  • Fixing of window                                                                          100% 
  • Fixing of window hood and wall belt                                        100% 

BLOCK D 

  • Fixing of window                                                                           100% 
  • Fixing of window hood and wall belt                                         50% 
  • POP ceiling installation                                                                 20% 
  • Plastering of Internal wall                                                           100% 
  • Plastering of external wall                                                           100% 
  • Setting of partition wall                                                               100% 
  • Electrical Piping on each floor                                                    100% 
  • Electrical wiring on each floor                                                    100% 
  • Plumbing work on each floor                                                       50% 

PICTURE SHOWING THE FRONT ELEVATION OF BLOCK A 

PICTURE SHOWING A COMPLETED WINDOW HOOD AND WALL BELT FITTINGS (SIDE ELEVATION) AT BLOCK A 

PICTURE SHOWING STAIRCASE BALUSTRADE AT BLOCK A 

 

PICTURE SHOWING BALCONY RAILINGS AT BLOCK A (BACK VIEW) 

PICTURE SHOWING POP CEILING WORKS AT BLOCK A ( LOUNGE)  

 

PICTURE SHOWING FRONT ELEVATION OF BLOCK C 

PICTURE SHOWING 3D VIEW OF BLOCK C 

PICTURE SHOWING POP CEILING WORKS AT BLOCK C (LOUNGE)  

PICTURE SHOWING POP CEILING WORKS AT BLOCK C (MASTER’S BDRM) 

 PICTURE SHOWING STAIRCASE BALUSTRADE AT BLOCK C 

PICTURE SHOWING BALCONY RAILINGS AT BLOCK C (BACK VIEW)