WORK PROGRESS
BLOCK A
- Second floor, forming of slab and beam to receive reinforcement in progress.
BLOCK B
- Setting of blocks on first floor ongoing.
BLOCK C
- Second floor, Ironwork, Electrical, and plumbing work ongoing ready to receive casting.
BLOCK D
- Taking of the level at unit 5 ongoing to receive formwork for first-floor slab.
APPENDIX
- Block A- picture showing Block A.
- Block B – Setting of blocks on first floor ongoing.
- Block C- picture of block.
Block D- Taking of the level at unit 5 going on to receive is first floor.
THANK YOU.