BLOCK A

  • Casting of ground, first, second and third-floor slab                                         100%
  • Blockwork on ground, first, second, and third-floor slab                                100%
  • Internal partition wall on ground, first, second & third-floor slab                 100%
  • Casting of extension column on ground , first, second,& third                      100%
  • Electrical piping down on ground and first floor only (Internal)                   100%
  • External electrical piping down (External).                                                         95%
  • Formwork and shuttering of third-floor extension column                              80%
  • Roof beam formwork and shuttering (in view).

BLOCK B

  • Casting of ground floor and First floor only                                                      100%
  • Blockwork on ground and First floor Slab                                                         95%
  • Slab reinforcement arrangement (Laying and Tieing) ( In view)
  • External electrical piping down                                                                           90%
  • Internal electrical piping down (Ground floor only)                                       60%

BLOCK C

  • Casting of ground and first-floor slab                                                               100%
  • Blockwork on ground and first floor slab                                                         100%
  • Formwork and shuttering of second floor slab                                               100%
  • External electrical piping down on block C                                                      100%
  • Slab reinforcement arrangement (Laying and Tieing) (in view)

BLOCK D

  • Casting of ground, first and second, third-floor slab                                    100%
  • Blockwork on ground, first and second floor only                                        100%
  • Blockwork and partition wall on third floor                                                  30%
  • Internal partition wall on ground, first and second-floor slab only          95%
  • Casting of extension columns on ground, first &, second floor only        100%
  • Electrical piping down ongoing.
  • External electrical piping down on block D                                                   95%

BLOCK E

  • Casting of ground, first and second-floor slab                                             100%
  • Blockwork on first and second floor                                                              95%
  • Extension column casting on ground, first and second floor                   100%
  • Internal partition walls on ground, first and second floor                        90%
  • Internal electrical piping down on first and send floor                              50%
  • External electrical piping down                                                                       95%
  • Formwork and shuttering for third-floor slab (in view).

                              SUMMARY OF STATE OF WORK

  • Block A, casting of first, second and third-floor slab 100%.
  • Blockwork of extension on GF,FF,SF 100%
  • Casting of extension column GF, FF, and SF 100%
  • Casting of first floor slab on block B 100%
  • Blockwork on first-floor slab (block B) 100%.
  • Block C, casting of first-floor slab 100%.
  • Blockwork on first floor (block C) 80%
  • Blockwork D casting of first and second-floor slab 100%.
  • Blockwork E, casting of floor Slab 100 %.
  • Blockwork on first-floor slab (block E) 100%.