BLOCK A
- Casting of ground, first, second and third-floor slab 100%
- Blockwork on ground, first, second, and third-floor slab 100%
- Internal partition wall on ground, first, second & third-floor slab 100%
- Casting of extension column on ground , first, second,& third 100%
- Electrical piping down on ground and first floor only (Internal) 100%
- External electrical piping down (External). 95%
- Formwork and shuttering of third-floor extension column 80%
- Roof beam formwork and shuttering (in view).
BLOCK B
- Casting of ground floor and First floor only 100%
- Blockwork on ground and First floor Slab 95%
- Slab reinforcement arrangement (Laying and Tieing) ( In view)
- External electrical piping down 90%
- Internal electrical piping down (Ground floor only) 60%
BLOCK C
- Casting of ground and first-floor slab 100%
- Blockwork on ground and first floor slab 100%
- Formwork and shuttering of second floor slab 100%
- External electrical piping down on block C 100%
- Slab reinforcement arrangement (Laying and Tieing) (in view)
BLOCK D
- Casting of ground, first and second, third-floor slab 100%
- Blockwork on ground, first and second floor only 100%
- Blockwork and partition wall on third floor 30%
- Internal partition wall on ground, first and second-floor slab only 95%
- Casting of extension columns on ground, first &, second floor only 100%
- Electrical piping down ongoing.
- External electrical piping down on block D 95%
BLOCK E
- Casting of ground, first and second-floor slab 100%
- Blockwork on first and second floor 95%
- Extension column casting on ground, first and second floor 100%
- Internal partition walls on ground, first and second floor 90%
- Internal electrical piping down on first and send floor 50%
- External electrical piping down 95%
- Formwork and shuttering for third-floor slab (in view).
SUMMARY OF STATE OF WORK
- Block A, casting of first, second and third-floor slab 100%.
- Blockwork of extension on GF,FF,SF 100%
- Casting of extension column GF, FF, and SF 100%
- Casting of first floor slab on block B 100%
- Blockwork on first-floor slab (block B) 100%.
- Block C, casting of first-floor slab 100%.
- Blockwork on first floor (block C) 80%
- Blockwork D casting of first and second-floor slab 100%.
- Blockwork E, casting of floor Slab 100 %.
- Blockwork on first-floor slab (block E) 100%.