SITE ACTIVITY REPORT FOR THE MONTH OF MARCH 2021 (GLENDALE PLUS, ABUJA)

white Avenue Real Estate

PICTORIAL VIEW OF GLENDALE PLUS STATE OF WORK.

BLOCK A

  • External wall screening                                                           100%
  • Installation of staircase balustrade                                       100%
  • Plastering of internal wall                                                       100%
  • Plastering of external wall                                                      100%
  • Electrical piping on each floor                                               100%

➢ Electrical wiring on each floor                                                    100%

  • Plumbing work on each floor                                                100%
  • Setting of partition wall                                                          100%
  • POP ceiling installation                                                          100%
  • Fixing of window                                                                      100%
  • Fixing of window hood and wall belt                                   100%
  • Tilling                                                                                          80%
  • Door installations                                                                     30%

BLOCK B

  • External wall screening                                                          100%
  • Plastering of external wall                                                      100%
  • Plastering of Internal wall                                                      100%
  • Setting of partition wall                                                          100%
  • Electrical piping on each floor                                               100%
  • Electrical wiring on each floor                                               100%
  • Plumbing work on each floor                                                 100%
  • Setting of partition wall                                                           100%
  • POP ceiling installation                                                           100%
  • Fixing of window                                                                      100%
  • Fixing of window hood and wall belt                                    100%
  • Tilling                                                                                          40%

BLOCK C

  • Wall painting (External)                                                            100%
  • Tyrolean wall finishes                                                                 95%
  • External wall screening                                                               100%
  • Plastering of Internal wall                                                          100%
  • Plastering of external wall                                                          100%
  • Setting of partition wall                                                               100%

➢ Electrical piping on each floor                                                        100%

➢ Electrical wiring on each floor                                                   100%

  • Plumbing work on each floor                                                    100%
  • POP ceiling installation                                                              100%
  • Fixing of window                                                                          100%
  • Fixing of window hood and wall belt                                       100%
  • Tilling                                                                                             50%
  • Door installation                                                                          30%

BLOCK D

  • Fixing of window                                                                        100%
  • Tilling                                                                                            10%
  • Fixing of window hood and wall belt                                      100%
  • POP ceiling installation                                                             90%
  • Plastering of Internal wall                                                         100%
  • Plastering of external wall                                                         100%
  • Setting of partition wall                                                              100%

➢ Electrical Piping on each floor                                                        100%

➢ Electrical wiring on each floor                                                         100%

➢ Plumbing work on each floor                                                           90%

 

SUMMARY

  • Fixing of window frame, window hood and grooving 100% done.
  • POP ceiling installation 99% done.
  • Plumbing work on each floor 95% done.
  • Electrical wiring on each floor (Block A&C) 100% done.
  • Plastering of internal and external walls (Block A and C) 100% done.
  • Installation of staircase Balustrade (Block A and C) 100% done.
  • External wall screeding 100 % done.
  • Internal wall screeding (ongoing) 20% done.
  • Tyrolean finishes on wall 100% done.
  • Wall painting (External) 100% done.
  • Laying of tiles (Soon to commence).

EXTERNAL WORKS

  • Earth works-70%
  • Plumbing works-70%
  • Fire and electrical provisions- 70%
  • Gate house-60%
  • Kerb work – 60%

APPENDIX

white avenue real estate

PICTURE SHOWING THE FRONT ELEVATION OF BLOCK A.

PICTURE SHOWING A COMPLETED WINDOW HOOD AND WALL BELT FITTINGS
AT BLOCK B.

PICTURE SHOWING COMPLETED FIXING OF WINDOWS AT BLOCK C

PICTURE SHOWING TILE OF THE LAST FLOOR IN BLOCK A.

PICTURE SHOWING TILE OF THE LAST FLOOR IN BLOCK A.

CONCLUSION

We keep ensuring the best quality control and finish touches to every item of work adhering to specifications. We are getting there.

                                                                                                                                  THANK YOU.