SITE ACTIVITY REPORT FOR THE MONTH OF MARCH 2021 (GLENDALE PLUS, ABUJA)
BLOCK A
- External wall screening 100%
- Installation of staircase balustrade 100%
- Plastering of internal wall 100%
- Plastering of external wall 100%
- Electrical piping on each floor 100%
➢ Electrical wiring on each floor 100%
- Plumbing work on each floor 100%
- Setting of partition wall 100%
- POP ceiling installation 100%
- Fixing of window 100%
- Fixing of window hood and wall belt 100%
- Tilling 80%
- Door installations 30%
BLOCK B
- External wall screening 100%
- Plastering of external wall 100%
- Plastering of Internal wall 100%
- Setting of partition wall 100%
- Electrical piping on each floor 100%
- Electrical wiring on each floor 100%
- Plumbing work on each floor 100%
- Setting of partition wall 100%
- POP ceiling installation 100%
- Fixing of window 100%
- Fixing of window hood and wall belt 100%
- Tilling 40%
BLOCK C
- Wall painting (External) 100%
- Tyrolean wall finishes 95%
- External wall screening 100%
- Plastering of Internal wall 100%
- Plastering of external wall 100%
- Setting of partition wall 100%
➢ Electrical piping on each floor 100%
➢ Electrical wiring on each floor 100%
- Plumbing work on each floor 100%
- POP ceiling installation 100%
- Fixing of window 100%
- Fixing of window hood and wall belt 100%
- Tilling 50%
- Door installation 30%
BLOCK D
- Fixing of window 100%
- Tilling 10%
- Fixing of window hood and wall belt 100%
- POP ceiling installation 90%
- Plastering of Internal wall 100%
- Plastering of external wall 100%
- Setting of partition wall 100%
➢ Electrical Piping on each floor 100%
➢ Electrical wiring on each floor 100%
➢ Plumbing work on each floor 90%
SUMMARY
- Fixing of window frame, window hood and grooving 100% done.
- POP ceiling installation 99% done.
- Plumbing work on each floor 95% done.
- Electrical wiring on each floor (Block A&C) 100% done.
- Plastering of internal and external walls (Block A and C) 100% done.
- Installation of staircase Balustrade (Block A and C) 100% done.
- External wall screeding 100 % done.
- Internal wall screeding (ongoing) 20% done.
- Tyrolean finishes on wall 100% done.
- Wall painting (External) 100% done.
- Laying of tiles (Soon to commence).
EXTERNAL WORKS
- Earth works-70%
- Plumbing works-70%
- Fire and electrical provisions- 70%
- Gate house-60%
- Kerb work – 60%
APPENDIX
CONCLUSION
We keep ensuring the best quality control and finish touches to every item of work adhering to specifications. We are getting there.