Glendale plus

PICTORIAL VIEW OF GLENDALE PLUS STATE OF WORK

 

APPENDIX

Glendale plus

PICTURE SHOWING THE COMPLETE FIXING OF WINDOWS ON BLOCK A

 

PICTURE SHOWING A COMPLETED WINDOW HOOD AND WALL BELT FITTINGS
AT BLOCK B.

 

PICTURE SHOWING COMPLETED WALL PAINTING AT BLOCK C

 

PICTURE SHOWING THE INTERLOCK AT BLOCK C AND D

 

PICTURE SHOWING TILE OF THE LAST FLOOR IN BLOCK A

BLOCK A

  • External wall screening                                   100%
  • Installation of staircase balustrade               100%
  • Plastering of internal wall                               100%
  • Plastering of external wall                               100%
  • Electrical piping on each floor                        100%
  • Electrical wiring on each floor                        100%
  • Plumbing work on each floor                          100%
  • Setting of partition wall                                   100%
  • POP Ceiling Installation                                  100%
  • Fixing of window                                              100%
  • Fixing of window hood and wall belt            100%
  • Tilling                                                                  90%
  • Door Installations                                            50%
  • Handrail Frame                                               100%
  • Veranda Painting                                             100%

BLOCK B

  • External wall screening                                 100%
  • Plastering of external wall                             100%
  • Plastering of Internal wall                             100%
  • Setting of partition wall                                 100%
  • Electrical piping on each floor                     100%
  • Electrical wiring on each floor                     100%
  • Plumbing work on each floor                       100%
  • Setting of partition wall                                100%
  • POP ceiling installation                                100%
  • Fixing of window                                            100%
  • Fixing of window hood and wall belt         100%
  • Tilling                                                               60%
  • Door Installation                                           5%
  • Handrail Frame                                             100%
  • Veranda Painting                                           100%
  • Sliding Door Installation                              100%

BLOCK C

  • Wall Painting (External)                            100%
  • Tyrolean all Finishes                                   95%
  • External wall Screeding                             100%
  • Plastering of Internal wall                         100%
  • Plastering of External wall                        100%
  • Setting of Partition wall                             100%
  • Electrical Piping on each Floor                 100%
  • Electrical Wiring on each Floor                100%
  • Plumbing work on each Floor                    100%
  • POP Ceiling Installation                             100%
  • Fixing of window                                          100%
  • Fixing of window Hood and Wall Belt     100%
  • Tilling                                                              90%
  • Door Installation                                          45%
  • Handrail Frame                                            100%
  • Veranda Painting                                          100%
  • Sliding Door Installation                             80%

BLOCK D

  • Fixing of Window                                      100%
  • Tilling                                                           40%
  • Fixing of Window Hood and Wall Belt 100%
  • POP ceiling Installation                           90%
  • Plastering of Internal Wall                      100%
  • Plastering of External Wall                     100%
  • Setting of Partition Wall                          100%
  • Electrical Piping on each Floor              100%
  • Electrical wiring on each Floor               100%
  • Plumbing Work on each Floor                90%
  • Door Installation                                       80%
  • Handrail Frame                                        100%
  • Veranda Painting                                     100%
  • Sliding Door Installation                         0%

                                         

 

 SUMMARY

  • Fixing of Window Frame, Window Hood and Grooving 100% done.
  • POP Ceiling Installation 99% done.
  • Plumbing Work on each Floor 95% done.
  • Electrical wiring on each Floor (Block A&C) 100% done.
  • Plastering of Internal and External walls (Block A and C) 100% done.
  • Installation of Staircase Balustrade (Block A and C) 100% done.
  • External wall screeding 100 % done.
  • Internal wall screeding (ongoing) 20% done.
  • Tyrolean Finishes on Wall 100% done.
  • Wall Painting (External) 100% done.
  • Laying of Tiles (Soon to commence).

 EXERNAL WORKS

  • Earth works-100% Done.
  • Plumbing works-80%
  • Fire and electrical provisions- 80% Done.
  • Gate house-50% Done.
  • Gen House- 50% Done.
  • Interlocking Works – 60% Done.
  • Fence Plastering And Painting – 60% Done.
  • Gate Installations – 100% Done.

 

CONCLUSION

We keep ensuring the best quality control and finish touches to every item of work adhering to specifications. We are getting there.

 

 

THANK YOU.