Phase 1 Report
APPENDIX
WORK SUMMARY
LOT – 7:
- Window dressing and divider Wall – 95%
LOT – 11: ROOF BEAM:
- Formwork – 100%
- Reinforcement work –100%
- Roof beam Casting – 100%
- External rendering (Plastering) – 95%
LOT – 12: ROOF BEAM:
- Formwork – 100%
- Reinforcement – 100%
- Casting – 100%
- Parapet wall – 100%
- Electrical piping – 100%
- Parapet boarding and casting – 80%
- External rendering (Plastering) – 90%
- Grooves – 90%
LOT – 14
- Colum boarding and casting – 80%
- Tie beam on two flat (To balance up with the Basement side).
- Formwork – 100%
- Iron work – 100%
- Casting – 100%
- Bamboo Scaffolding – 85%
- Roof beam formwork – Preparation.
LOT – 15: ROOF BEAM:
- Formwork – 100%
- Reinforcement work – 100%
- Parapet blockwork – 100%
- Parapet column boarding and casting – 100%
- External rendering (Plastering) – 95%
- Grooves – 70%
LOT – 16
- Slab casting – 100% (Just little Recess to Balance up).
- Blockwork – 98%
- Column boarding and casting – 85%
FD – 1-5:
- Roof Beam formwork – 100%.
- Bamboo Scaffolding – 100%.
FD – 9:
- General maintenance Ongoing
FD – 2-4:
- Reinforcement work – 100%.
- Bamboo Scaffolding – 100%.
- Casting – 30%.
GATEHOUSE:
- Casting of the remaining columns – 100%
- Blockwork in between the columns – 100%
- Arc Wall rendering, dressing of Columns, and maintenance.
GENERAL WORKS
- Fence wall along theme park (blockwork).
- Backfilling at the back of lot 3.
- Bridge wall leveling boarding (completed) waiting for casting.
THANK YOU.