APPENDIX

CC BLOCK

Block A- Ironwork on lintel ongoing.

COLOR CODE

Block B – Second-floor slab forming ongoing.

COLOR CODE

Block C- Ironwork on roof beam ongoing.

Block D- First-floor slab iron complete.

WORK PROGRESS

Block A.

  • Blockwork ongoing on the second floor and the master bedrooms are modified.
  • Nailing of lintel and column ongoing.
  • Ironwork on lintel ongoing.

Block B.

  • Second-floor slab forming ongoing.
  • Blockwork ongoing at ground floor in some areas.

Block C.

  • Roof beam caisson ongoing to receive iron.
  • Master bedroom modification ongoing.
  • Cleaning of the units ongoing.
  • Ironwork on Roof beam ongoing.

Block D.

  • First-floor slab iron complete.

OTHER ACTIVITIES: General cleaning of the compound with Bulldozer done Saturday.

 

 

                                                                                                                                     THANK YOU.