APPENDIX

Picture showing the External wall plastering on Block A.

 

Picture showing Block B.

 

Picture showing Formwork and Shuttering to Third-floor slab on Block C.

 

A Picture of Block D

 

Picture showing the Blockwork on third-floor slab on Block E

 

BLOCK A

  • External Mechanical Electrical Piping down (external).                    100%
  • Formwork and Shuttering of Third Floor Extension Column.        100%
  • Roof Beam Formwork and Shuttering                                                  100%
  • Concrete Casting to Roof beam Formwork                                            100%
  • Roof trusses/Carcassing                                                                             100%
  • Installation of parapet (Polystyrene)                                                         100%
  • External wall plastering                                                                                30%
  • Roofing (Step Tiles) In view.

 BLOCK B

  • Formwork and shuttering to Second Floor Slab                               100%
  • Slab Reinforcement Arrangement (Laying and Tieing)                  100%
  • Concrete Casting to Second Floor Slab                                                100%
  • Blockwork on Second Floor slab                                                           100%
  • Formwork and Shuttering to Third-floor slab                                   100%
  • Reinforcement to third floor slab                                                         40%
  • Mechanical and Electrical installation to third-floor slab (In view).

 BLOCK C

  • Slab reinforcement arrangement (Second Floor)                             100%
  • Concrete Casting    to Second Floor Slab                                              100%
  • Blockwork on Second Floor Slab                                                           100%
  • Formwork and Shuttering to Third-floor slab                                   40%
  • Reinforcement to third-floor slab (In view).

 

BLOCK D

  • Blockwork and Partition wall on Third Floor Slab                         100%
  • Roof Beam Formwork and Shuttering                                              100%
  • Installation of parapet (Polystyrene)                                                 100%
  • Roof Trusses/Carcassing                                                                     10%
  • External mechanical and Electrical Piping down                           100%
  • External wall Plastering                                                                       10%

 

 

BLOCK E

  • Formwork and Shuttering for Third Floor Slab                              100%
  • Mechanical and Electrical installation to third-floor slab             100%
  • Reinforcement to third-floor slab                                                       100%
  • Concrete casting of third-floor slab                                                    100%
  • Blockwork on third-floor slab                                                               10%
  • Formwork and Shuttering to Roof beam (In view)

 

SUMMARY OF STATE OF WORK

  • Roof Beam Formwork and Shuttering 100% (Block A)
  • Formwork and Shuttering of Third Floor Extension Column 100% (Block A)
  • Formwork and Shuttering to Second Floor Slab 100% (Block B)
  • Slab Reinforcement arrangement (Laying and Tieing) 100% (Block B)
  • Slab Reinforcement arrangement (Second Floor) 100% (Block C)
  • Concrete Casting to Second Floor Slab 100%  (Block C)
  • Blockwork and Partition Wall on Third Floor Slab 100% (Block D)
  • Reinforcement to Third Floor Slab 100% (Block E)

 

 