PICTORIAL VIEW OF GLENDALE PLUS STATE OF WORK

APPENDIX

PICTURE SHOWING COMPLETED WALL PAINTING ON BLOCK A

 

PICTURE SHOWING A COMPLETED WINDOW HOOD AND WALL BELT FITTINGS
AT BLOCK B.

 

PICTURE SHOWING COMPLETED WALL PAINTING ON BLOCK C

 

PICTURE SHOWING BLOCK D

 

THE INSIDE OF BLOCK A

 

PICTURE SHOWING THE ONGOING CONSTRUCTION OF THE OVERHEAD TANK

 

PICTURE SHOWING THE GATEHOUSE

 

  BLOCK A

  • Plastering of internal wall                                 100%
  • Plastering of external wall                                 100%
  • Electrical piping on each floor                          100%
  • Electrical wiring on each floor                          100%
  • Plumbing work on each floor                            100%
  • Setting of partition wall                                      100%
  • POP Ceiling Installation                                     100%
  • Fixing of window                                                  100%
  • Fixing of window hood and wall belt                100%
  • Handrail Frame                                                     100%
  • Verander Painting                                                 100%
  • Internal Tilling                                                        85%
  • External Tilling                                                        50%
  • Internal Doors installation                                    60%
  • External Doors installation                                   65%
  • Kitchen Cabinets installation                               70%
  • Internal wall painting                                            70%
  • Stair hall screening                                                 90%
  • Sanitary wares installation                                   5%
  • Fire Hydrants installation                                     90%

 

BLOCK B

  • External wall screening                                  100%
  • Plastering of external wall                              100%
  • Plastering of Internal wall                              100%
  • Setting of partition wall                                  100%
  • Electrical piping on each floor                       100%
  • Electrical wiring on each floor                       100%
  • Plumbing work on each floor                          100%
  • Setting of partition wall                                   100%
  • POP ceiling installation                                   100%
  • Fixing of window                                                100%
  • Fixing of window hood and wall belt             100%
  • Handrail Frame                                                 100%
  • Varrander Painting                                          100%
  • Sliding Door Installation                                  100%
  • Internal Tilling                                                  85%
  • External Tilling                                                 50%
  • Internal Doors installation                            60%
  • External Doors installation                           65%
  • Kitchen Cabinets installation                        70%
  • Internal wall painting                                     70%
  • Stair hall screening                                          90%
  • Sanitary wares installation                               5%
  • Fire Hydrants installation                               90%

                 BLOCK C

  • Wall Painting (External)                           100%
  • Tyrolean all Finishes                                   95%
  • External wall Screeding                               100%
  • Plastering of Internal wall                          100%
  • Plastering of External wall                          100%
  • Setting of Partition wall                               100%
  • Electrical Piping on each Floor                   100%
  • Electrical Wiring on each Floor                  100%
  • Plumbing work on each Floor                      100%
  • POP Ceiling Installation                               100%
  • Fixing of window                                            100%
  • Fixing of window Hood and Wall Belt        100%
  • Tilling                                                                 90%
  • Door Installation                                               45%
  • Handrail Frame                                               100%
  • Varrander Painting                                         100%
  • Sliding Door Installation                              80%
  • Internal Tilling                                                85%
  • External Tilling                                                50%
  • Internal Doors installation                           60%
  • External Doors installation                           65%
  • Kitchen Cabinets installation                       70%
  • Internal wall painting                                    70%
  • Stair hall screeding                                         90%
  • Sanitary wares installation                            5%
  • Fire Hydrants installation                            90%

 

BLOCK D

  • Fixing of Window                                        100%
  • Fixing of Window Hood and Wall Belt  100%
  • POP ceiling Installation                             90%
  • Plastering of Internal Wall                       100%
  • Plastering of External Wall                      100%
  • Setting of Partition Wall                           100%
  • Electrical Piping on each Floor               100%
  • Electrical wiring on each Floor                100%
  • Plumbing Work on each Floor                  90%
  • Handrail Frame                                          100%
  • Varrander Painting                                    100%
  • Internal Tilling                                             85%
  • External Tilling                                              50%
  • Internal Doors installation                        60%
  • External Doors installation                        65%
  • Kitchen Cabinets installation                    70%
  • Internal wall painting                                  70%
  • Stair hall screening                                      90%
  • Sanitary wares installation                            5%
  • Fire Hydrants installation                           90%

 

 SUMMARY

  • Fixing of Window Frame, Window Hood, and Grooving 100% done.
  • POP Ceiling Installation 100% done.
  • Plumbing Work on each Floor 95% done.
  • Electrical wiring on each Floor (Block A&C) 100% done.
  • Plastering of Internal and External walls (Block A and C) 100% done.
  • Installation of Staircase Balustrade (Block A and C) 100% done.
  • External wall screeding 100 % done.
  • Internal wall painting 70% done.
  • Tyrolean Finishes on Wall 100% done.
  • Wall Painting (External) 100% done.

 

 EXTERNAL WORKS

  • Earth works-100% Done.
  • Plumbing works-80%
  • Fire and Electrical provisions- 80% Done.
  • Gate House-90% Done.
  • Gen House- 50% Done.
  • Interlocking Works – 60% Done.
  • Fence Plastering And Painting – 60% Done.
  • Gate Installations – 100% Done.
  • Fire Hydrants installation – 90% Done.
  • Overhead Tank – 15% Done

 

CONCLUSION

We keep ensuring the best quality control and finish touches to every item of work adhering to specifications. We are getting there.

 

 

THANK YOU.