APPENDIX
BLOCK A
- Plastering of internal wall 100%
- Plastering of external wall 100%
- Electrical piping on each floor 100%
- Electrical wiring on each floor 100%
- Plumbing work on each floor 100%
- Setting of partition wall 100%
- POP Ceiling Installation 100%
- Fixing of window 100%
- Fixing of window hood and wall belt 100%
- Handrail Frame 100%
- Verander Painting 100%
- Internal Tilling 85%
- External Tilling 50%
- Internal Doors installation 60%
- External Doors installation 65%
- Kitchen Cabinets installation 70%
- Internal wall painting 70%
- Stair hall screening 90%
- Sanitary wares installation 5%
- Fire Hydrants installation 90%
BLOCK B
- External wall screening 100%
- Plastering of external wall 100%
- Plastering of Internal wall 100%
- Setting of partition wall 100%
- Electrical piping on each floor 100%
- Electrical wiring on each floor 100%
- Plumbing work on each floor 100%
- Setting of partition wall 100%
- POP ceiling installation 100%
- Fixing of window 100%
- Fixing of window hood and wall belt 100%
- Handrail Frame 100%
- Varrander Painting 100%
- Sliding Door Installation 100%
- Internal Tilling 85%
- External Tilling 50%
- Internal Doors installation 60%
- External Doors installation 65%
- Kitchen Cabinets installation 70%
- Internal wall painting 70%
- Stair hall screening 90%
- Sanitary wares installation 5%
- Fire Hydrants installation 90%
BLOCK C
- Wall Painting (External) 100%
- Tyrolean all Finishes 95%
- External wall Screeding 100%
- Plastering of Internal wall 100%
- Plastering of External wall 100%
- Setting of Partition wall 100%
- Electrical Piping on each Floor 100%
- Electrical Wiring on each Floor 100%
- Plumbing work on each Floor 100%
- POP Ceiling Installation 100%
- Fixing of window 100%
- Fixing of window Hood and Wall Belt 100%
- Tilling 90%
- Door Installation 45%
- Handrail Frame 100%
- Varrander Painting 100%
- Sliding Door Installation 80%
- Internal Tilling 85%
- External Tilling 50%
- Internal Doors installation 60%
- External Doors installation 65%
- Kitchen Cabinets installation 70%
- Internal wall painting 70%
- Stair hall screeding 90%
- Sanitary wares installation 5%
- Fire Hydrants installation 90%
BLOCK D
- Fixing of Window 100%
- Fixing of Window Hood and Wall Belt 100%
- POP ceiling Installation 90%
- Plastering of Internal Wall 100%
- Plastering of External Wall 100%
- Setting of Partition Wall 100%
- Electrical Piping on each Floor 100%
- Electrical wiring on each Floor 100%
- Plumbing Work on each Floor 90%
- Handrail Frame 100%
- Varrander Painting 100%
- Internal Tilling 85%
- External Tilling 50%
- Internal Doors installation 60%
- External Doors installation 65%
- Kitchen Cabinets installation 70%
- Internal wall painting 70%
- Stair hall screening 90%
- Sanitary wares installation 5%
- Fire Hydrants installation 90%
SUMMARY
- Fixing of Window Frame, Window Hood, and Grooving 100% done.
- POP Ceiling Installation 100% done.
- Plumbing Work on each Floor 95% done.
- Electrical wiring on each Floor (Block A&C) 100% done.
- Plastering of Internal and External walls (Block A and C) 100% done.
- Installation of Staircase Balustrade (Block A and C) 100% done.
- External wall screeding 100 % done.
- Internal wall painting 70% done.
- Tyrolean Finishes on Wall 100% done.
- Wall Painting (External) 100% done.
EXTERNAL WORKS
- Earth works-100% Done.
- Plumbing works-80%
- Fire and Electrical provisions- 80% Done.
- Gate House-90% Done.
- Gen House- 50% Done.
- Interlocking Works – 60% Done.
- Fence Plastering And Painting – 60% Done.
- Gate Installations – 100% Done.
- Fire Hydrants installation – 90% Done.
- Overhead Tank – 15% Done
CONCLUSION
We keep ensuring the best quality control and finish touches to every item of work adhering to specifications. We are getting there.
THANK YOU.