Phase 1 Report

APPENDIX

Cedarwood city

Picture showing the Screeding level on Lot 15

Picture showing the Drainage.

Picture showing the Screeding level on Lot 14.

LOT 11- Reinforcement work completed.

Lot 12- Copping 100% done.

Retaining wall by the river ongoing.

Lot 13, Bamboo scaffolding completed

Picture of the Sport Center

Picture showing the Bridge

A picture of F-D 1-5

A picture of F-D 6-9.

Picture showing the Park

Picture showing water Fountain.

Picture showing the Gatehouse.

WORK SUMMARY

LOT – 3:

  • Roofing ongoing.

 

LOT – 4:

  • Bamboo scaffolding – 70%

LOT- 11

  • Copping – 100%
  • Internal rendering – 60%

LOT – 12:

  • Internal rendering – 90%
  • Copping – 100%

            LOT – 13

  • Bamboo scaffolding – 100%

 

LOT – 14:

  • External rendering – 100%
  • Internal rendering – 90%
  • Screeding – 100%

LOT – 15

  • Copping – 50%
  • Internal rendering – 50%

 

FD – 1-3:

  • Roofing – 100%
  • Bamboo Scaffolding – 100%.
  • Plastering – 100%

 

FD – 4:

  • External rendering and RB casted.
  • Plastering – 100%

 

FD –   5: 

  • Roof beam casting – 100%
  • Plastering– 100%

 

FD –   6: 

  • Casted – 100%
  • Plastering – 100%

 

FD – 10 & 11: Demolished.

 

GATEHOUSE:

  • Casting of the remaining columns – 100%
  • Blockwork in between the columns – 100%
  • Arc formwork – 100%

RETAINING WALL: By the river ongoing.

GENERAL WORKS

  • Lot 3, Roofing ongoing.
  • All FD’s has been plastered.

                                                        THANK YOU.