Phase 1 Report
APPENDIX
WORK SUMMARY
LOT – 3:
- Roofing ongoing.
LOT – 4:
- Bamboo scaffolding – 70%
LOT- 11
- Copping – 100%
- Internal rendering – 60%
LOT – 12:
- Internal rendering – 90%
- Copping – 100%
LOT – 13
- Bamboo scaffolding – 100%
LOT – 14:
- External rendering – 100%
- Internal rendering – 90%
- Screeding – 100%
LOT – 15
- Copping – 50%
- Internal rendering – 50%
FD – 1-3:
- Roofing – 100%
- Bamboo Scaffolding – 100%.
- Plastering – 100%
FD – 4:
- External rendering and RB casted.
- Plastering – 100%
FD – 5:
- Roof beam casting – 100%
- Plastering– 100%
FD – 6:
- Casted – 100%
- Plastering – 100%
FD – 10 & 11: Demolished.
GATEHOUSE:
- Casting of the remaining columns – 100%
- Blockwork in between the columns – 100%
- Arc formwork – 100%
RETAINING WALL: By the river ongoing.
GENERAL WORKS
- Lot 3, Roofing ongoing.
- All FD’s has been plastered.
THANK YOU.