APPENDIX

Picture showing the Roofing on Block A

 

Picture showing Blockwork and Reinforcement to extension column on Block B.

 

Picture showing Blockwork on third-floor slab on Block C.

 

A Picture of Block D

 

Picture showing roof beam and parapet on Block E.

 

BLOCK A

  • Roofing (100%)
  • External wall plastering (96%)
  • Internal wall plastering (15%)
  • Wall skirting & grooves Installation (100%)

BLOCK B

  • Reinforcement to third floor (100%)
  • Casting of third-floor slab (100%)
  • Blockwork to third-floor slab (90%)
  • Extension columns & lintel to third floor (In view)

BLOCK C

  • Formwork and shuttering to third-floor slab (100%)
  • Reinforcement to third-floor slab (100%)
  • Blockwork to third-floor slab (70%)
  • Extension columns and lintel to third floor (In view)

BLOCK D

  • Roof trusses/carcassing (100%)
  • Roofing – step tiles (100%)
  • External wall plastering (80%)
  • Wall skirting & grooves Installation (20%)

 

BLOCK E

  • Blockwork on third-floor slab (100%)
  • Extension columns and lintel to third floor (100%)
  • Roof beam formwork & shuttering (100%)
  • Concrete casting to Roof beam formwork (100%)
  • External wall plastering (30%)
  • Roof trusses/carcassing (In view)

 

SUMMARY OF STATE OF WORK

  • Roof beam formwork & shuttering 100% done on Block E.
  • Concrete casting to Roof beam formwork 100% done on Block E.
  • Formwork and shuttering to third floor slab 100% done on Block C.
  • Reinforcement to third floor slab 100% done on Block C.
  • Reinforcement to third floor 100% done on Block B
  • Casting of third floor slab 100% done on Block B.

 

 

 

 THANK YOU.