APPENDIX
WORK SUMMARY
LOT – 3:
- Roofing – 100%
LOT – 4:
- Bamboo scaffolding – 100%
- Copping – 100%
LOT – 5:
- Internal rendering – 45%
- Copping casting ongoing.
LOT – 6:
- Internal rendering – 35%
- Copping formwork completed.
LOT – 7:
- Internal rendering – 40%
LOT-11
- Copping – 100%
- Internal rendering – 85%
LOT – 12:
- Internal rendering – 90%
- Copping – 100%
LOT – 13
- Copping – 100%
- Internal rendering – 75%
LOT – 14:
- External rendering – 100%
- Internal rendering – 90%
- Screeding – 100%
- Copping – 100%
LOT – 15
- Copping – 100%
- Internal rendering – 70%
FD – 1:
- Internal rendering – 60%
FD – 1-7:
- copped
FD – 4-8:
- Waiting for roof covering.
FD – 3- 6:
- Screeding completed.
FD – 10 & 11: Demolished.
GATEHOUSE:
- Casting of the remaining columns – 100%
- Blockwork in between the columns – 100%
- Arc formwork – 100%
RETAINING WALL: By the river ongoing.
GENERAL WORKS
- Soakaway between Lot 8 & 9 slab (Deck level).
- All FD’s has been plastered.
THANK YOU.