APPENDIX

Block A- Reinforcement work on roof slab completed

 

Block B – Blockwork to lintel level

 

Block C- Roof slab cantilever reinforcements.

 

WORK PROGRESS

Block A.

  • Electrical pipping work – 40%
  • Roof slab Cantilever formwork completed.
  • Reinforcement work on roof slab completed.
  • Electrical work is in progress.
  • Plumbing work is in progress.
  • Casting in view (28th July 26, 2021)
  • Scaffold round the building completed.
  • Internal plastering at A5 – 70%, A3 – 50%, A1 -25%.
  • Block A external – 15%

Block B.

  • Scaffold round the building                        50%
  • Second floor slab casting 100%
  • Setting out of blocks on second floor        100%
  • Blockwork to lintel level 100%
  • Extension column mounting 100%
  • Column and lintel formwork                        25%
  • Lintel reinforcements                                20%
  • Casting of columns and lintels                     10%
  • Electrical pipping work                               40%

Block C.

  • Roof slab cantilever reinforcements 100%
  • Electrical work on roof slab 100%
  • Casting of Roof slab cantilever  100%
  • Electrical pipping work              70%

Block D.

  • First floor slab form 100%
  • Lintel and column formwork 100%
  • Lintel and column casting 100%
  • Blockwork to second slab level  100%
  • Second floor slab formwork 90%
  • Slab reinforcement work 10%

 

CONCLUSION: Work is in progress using the best quality in every items of work and making sure that the project will be completed in stipulated time.

 

 