APPENDIX
WORK PROGRESS
Block A.
- Electrical pipping work – 40%
- Roof slab Cantilever formwork completed.
- Reinforcement work on roof slab completed.
- Electrical work is in progress.
- Plumbing work is in progress.
- Casting in view (28th July 26, 2021)
- Scaffold round the building completed.
- Internal plastering at A5 – 70%, A3 – 50%, A1 -25%.
- Block A external – 15%
Block B.
- Scaffold round the building 50%
- Second floor slab casting 100%
- Setting out of blocks on second floor 100%
- Blockwork to lintel level 100%
- Extension column mounting 100%
- Column and lintel formwork 25%
- Lintel reinforcements 20%
- Casting of columns and lintels 10%
- Electrical pipping work 40%
Block C.
- Roof slab cantilever reinforcements 100%
- Electrical work on roof slab 100%
- Casting of Roof slab cantilever 100%
- Electrical pipping work 70%
Block D.
- First floor slab form 100%
- Lintel and column formwork 100%
- Lintel and column casting 100%
- Blockwork to second slab level 100%
- Second floor slab formwork 90%
- Slab reinforcement work 10%
CONCLUSION: Work is in progress using the best quality in every items of work and making sure that the project will be completed in stipulated time.