APPENDIX
BLOCK A
- Roofing (100%)
- Electrical piping down on each floor – 100%
- Plumbing works on each floor – 100%
- Setting of partition wall – 100%
- Fixing of wall skirting & belt -100%
- Plastering of internal wall – 60%
- Pop ceiling installation – in view.
BLOCK B
- Extension columns & lintel to third floor – 100%
- Blockwork on third floor – 100%
- Setting of partition wall – 95%
- Roof beam formwork & shuttering – 100%
- Reinforcement to roof beam – 100%
- Concrete casting of roof beam – 100%
- Installation of polystyrene(parapet) – 100%
- Roof trusses installation – 20%
- Roofing (step tiles installation) in view.
BLOCK C
- Extension columns and lintel to third floor – 100%
- Blockwork to third floor -100%
- Setting of partition wall – 90%
- Roof beam formwork & shuttering – 100%
- Reinforcement to roof beam – 100%
- Concrete casting of roof beam – 80%
- Installation of polystyrene (parapet) – 100%
- Roof trusses installation – in view
BLOCK D
- Roofing – 100%
- Electrical piping down on each floor – 60%
- Plumbing works on each floor – 20%
- Setting of partition wall -100%
- Fixing of wall skirting & belts – 90%
- Plastering of external wall – 80%
- Plastering of internal wall – 30%
- Pop ceiling installation – in view
BLOCK E
- Blockwork on third floor slab (100%)
- Setting of partition wall – 100%
- Roof beam formwork & shuttering – 100%
- Concrete casting to Roof beam formwork (100%)
- Roof trusses installation – 100%
- Roofing (step tiles installation – 30% (In progress)
- Plastering of external wall – 95%
- Plastering of internal wall – in view
SUMMARY OF STATE OF WORK
- Roof beam formwork & shuttering 100% done on Block E.
- Concrete casting to Roof beam formwork 100% done on Block E.
- Formwork and shuttering to third floor slab 100% done on Block C.
- Reinforcement to third floor slab 100% done on Block C.
- Reinforcement to third floor 100% done on Block B
- Casting of third floor slab 100% done on Block B.
THANK YOU.