APPENDIX

Picture showing the Roofing on Block A

Concrete casting of roof beam on Block B

Reinforcement to roof beam on Block C.

Roofing on Block D

Roof beam and parapet on Block E

BLOCK A

  • Roofing (100%)
  • Electrical piping down on each floor – 100%
  • Plumbing works on each floor – 100%
  • Setting of partition wall – 100%
  • Fixing of wall skirting & belt -100%
  • Plastering of internal wall – 60%
  • Pop ceiling installation – in view.

 BLOCK B

  • Extension columns & lintel to third floor – 100%
  • Blockwork on third floor – 100%
  • Setting of partition wall – 95%
  • Roof beam formwork & shuttering – 100%
  • Reinforcement to roof beam – 100%
  • Concrete casting of roof beam – 100%
  • Installation of polystyrene(parapet) – 100%
  • Roof trusses installation – 20%
  • Roofing (step tiles installation) in view.

 BLOCK C

  • Extension columns and lintel to third floor – 100%
  • Blockwork to third floor -100%
  • Setting of partition wall – 90%
  • Roof beam formwork & shuttering – 100%
  • Reinforcement to roof beam – 100%
  • Concrete casting of roof beam – 80%
  • Installation of polystyrene (parapet) – 100%
  • Roof trusses installation – in view

BLOCK D

  • Roofing – 100%
  • Electrical piping down on each floor – 60%
  • Plumbing works on each floor – 20%
  • Setting of partition wall -100%
  • Fixing of wall skirting & belts – 90%
  • Plastering of external wall – 80%
  • Plastering of internal wall – 30%
  • Pop ceiling installation – in view

BLOCK E

  • Blockwork on third floor slab (100%)
  • Setting of partition wall – 100%
  • Roof beam formwork & shuttering – 100%
  • Concrete casting to Roof beam formwork (100%)
  • Roof trusses installation – 100%
  • Roofing (step tiles installation – 30% (In progress)
  • Plastering of external wall – 95%
  • Plastering of internal wall – in view

 

SUMMARY OF STATE OF WORK

  • Roof beam formwork & shuttering 100% done on Block E.
  • Concrete casting to Roof beam formwork 100% done on Block E.
  • Formwork and shuttering to third floor slab 100% done on Block C.
  • Reinforcement to third floor slab 100% done on Block C.
  • Reinforcement to third floor 100% done on Block B
  • Casting of third floor slab 100% done on Block B.