APPENDIX
WORK PROGRESS
Block A.
- General electrical pipping work – 80%
- Roof electrical pipe works – 40%
- General Plumbing work – 60%
- Roof parapet work – 100%
- General internal plaster at A5 – 80%, A4 – 60%, A3 -50%, A2 -60% A1 -80%
- General external plaster– 35%
Block B.
- Scaffold round the building – 100%
- Column and lintel formwork – 100%
- Casting of columns and lintels – 100%
- General internal pipe works – 40%
- Block work to roof beam level – 100%
- Roof beam formwork and reinforcement in view.
- Roof parapet reinforcements and formworks in view.
- Roof parapet casting in view.
- Internal plastering in view.
- General plumbing work – 45%
Block C.
- General internal plastering works C1-50%, C2-90%, C3-50%, C4-40%, C5-40%
- General external plastering – 72%
- General electrical work – 80%
Block D.
- Second-floor slab formwork 100%
- Second-floor slab reinforcement 100%
- Second-floor slab casting 100%
CONCLUSION: Work is in progress using the best quality in every items of work and making sure that the project will be completed in stipulated time
THANK YOU.