APPENDIX

Block A- Roof electrical pipe works – 40% done.

 

Block B – Block work to roof beam level – 100% done.

 

Block C- Roof slab cantilever reinforcements

 

Block D- Second-floor slab formwork -100% done

 

WORK PROGRESS

Block A.

  • General electrical pipping work – 80%
  • Roof electrical pipe works – 40%
  • General Plumbing work – 60%
  • Roof parapet work – 100%
  • General internal plaster at A5 – 80%, A4 – 60%, A3 -50%, A2 -60% A1 -80%
  • General external plaster– 35%

Block B.

  • Scaffold round the building –    100%
  • Column and lintel formwork – 100%
  • Casting of columns and lintels – 100%
  • General internal pipe works –  40%
  • Block work to roof beam level – 100%
  • Roof beam formwork and reinforcement in view.
  • Roof parapet reinforcements and formworks in view.
  • Roof parapet casting in view.
  • Internal plastering in view.
  • General plumbing work – 45%

Block C.

  • General internal plastering works C1-50%, C2-90%, C3-50%, C4-40%, C5-40%
  • General external plastering – 72%
  • General electrical work – 80%

Block D.

  • Second-floor slab formwork 100%
  • Second-floor slab reinforcement 100%
  • Second-floor slab casting       100%

 

CONCLUSION: Work is in progress using the best quality in every items of work and making sure that the project will be completed in stipulated time

 