Phase 1 Report
APPENDIX
WORK SUMMARY
LOT – 3:
- Roofing – 100%
LOT – 4:
- Bamboo scaffolding – 100%
- Copping – 100%
LOT – 5:
- Internal rendering – 65%
- Copping – 100%
LOT – 6:
- Internal rendering – 55%
- Copping formwork completed.
LOT – 7:
- Internal rendering – 40%
LOT – 11:
- Copping – 100%
- Internal rendering – 90%
LOT – 12:
- Internal rendering – 90%
- Copping – 100%
- Roof trusses – 95%
LOT – 13
- Copping – 100%
- Internal rendering – 90%
LOT – 14:
- External rendering – 100%
- Internal rendering – 90%
- Screeding – 100%
- Copping – 100%
- Roof trusses – 20%
LOT – 15
- Copping – 100%
- Internal rendering – 70%
FD – 1: Internal rendering – 80%
FD – 2: Internal rendering – 60%
FD – 3: Internal rendering – 20%
FD – 5: Internal rendering – 80%
FD – 6: internal rendering – 90%
FD – 1-7: Roofing – 100%
GATEHOUSE:
- Casting of the remaining columns – 100%
- Blockwork in between the columns – 100%
- Arc formwork – 100%
- All rendering at the house – 95 %
RETAINING WALL:
- By the River ongoing.
- By the Gatehouse – 85%
- By the bridge to F-D 1 ongoing.
GENERAL WORKS
- Soakaway between Lot 8 & 9 slab (Deck level).
- All FD’s has been plastered.
- The new four-bedroom excavation is ongoing.
THANK YOU.