Plastering of internal wall 100% done on Block A.

 

Picture showing complete roofing on Block B

 

Roof trusses installation 100% done on Block C.

 

Plumbing work on each floor 100% done on Block D.

 

Picture showing the roofing on Block E

 

BLOCK A

  • Plastering of internal wall – 100% done.
  • Fixing of electrical cables (Wiring) – in view.
  • Installation of Pop ceiling – in view.

 

 BLOCK B

  • Setting of partition wall – 100% done.
  • Roof trusses installation – 100% done.
  • Roofing (step tiles installation)-100% done.
  • Electrical Piping down on each floor – 60% done.
  • Plumbing works on each floor – 80% done.
  • Plastering of internal wall – 20% done.
  • Plastering of external wall – 20% done.
  • Fixing of wall skirting’s and grooves – in view.

  BLOCK C

  • Setting of partition wall – 100% done.
  • Concrete casting of roof beam – 100% done.
  • Installation of polystyrene (parapet) – 100% done.
  • Roof trusses installation – 100% done.
  • Roofing (Step tiles installation) – 50% done.
  • Electrical Piping down on each floor – 40% done.
  • Plastering of internal wall – 15% done.
  • Plastering of external wall – 15% done.
  • Plumbing work on each floor – in view.
  • Fixing of wall skirting’s and grooves – in view.

BLOCK D

  • Electrical piping down on each floor – 90% done.
  • Plumbing works on each floor – 100% done.
  • Fixing of wall skirting’s and grooves – 95% done.
  • Plastering of internal wall – 100% done.
  • Plastering of external wall – 95% done.
  • Fixing of electrical cables (Wiring) – in view.
  • Installation of Pop ceiling – in view.

 

BLOCK E

  • Roofing (step tiles installation) – 100% done.
  • Electrical piping down on each floor – 40% done.
  • Plastering of internal wall – 15% done.
  • Plastering of external wall – 100% done.
  • Plumbing works on each floor – in view.

SUMMARY OF STATE OF WORK

  • Plastering of internal wall 100% done on Block A.
  • Setting of partition wall 100% done on Block B
  • Roof trusses installation 100% done Block B.
  • Formwork and shuttering to third floor slab 100% done on Block C.
  • Reinforcement to third floor slab 100% done on Block C.
  • Plumbing works on each floor 100% done on Block D.
  • Roofing (step tiles installation) 100% done on Block E.

 

 