Phase 1 Report
APPENDIX
WORK SUMMARY
LOT – 3:
- Roofing – 100%
LOT – 4:
- Bamboo scaffolding – 100%
- Rafter – 100%
LOT – 5:
- Internal rendering – 85%
- Copping – 100%
- Rafter – 100%
LOT – 6:
- Internal rendering – 95%
- Copping formwork completed.
- Rafter – 100%
LOT – 7:
- Internal rendering – 95%
- Rafter – 100%
- PPR piping and waste dropping.
LOT – 8:
- Roofed
LOT – 11:
- Copping – 100%
- Internal rendering – 90%
- Roofed
LOT – 12:
- Internal rendering – 95%
- Copping – 100%
- Roof trusses – 95%
LOT – 13
- Copping – 100%
- Internal rendering – 95%
LOT – 14:
- External rendering – 100%
- Internal rendering – 95%
- Screeding – 100%
- Copping – 100%
- Roof trusses – 20%
LOT – 15
- Copping – 100%
- Internal rendering – 70%
LOT – 16:
- Slab formwork completed.
- Reinforcement – 90%
- Basement plastered.
LOT – 17:
- Basement stepdown 1 Backfilled.
- Blockwork at 80% on stepdown 2.
FD – 9, 8, 7, 6, and 5: Soakaway block work and column completed
GATEHOUSE:
- Wall tiled.
- Maintenance work ongoing.
RETAINING WALL:
- By the River ongoing.
- By the Gatehouse – 85%
- By the bridge to F-D 1 ongoing.
GENERAL WORKS
- FD – 9 , 8, 7, 6, and 5: Soakaway block work and column completed.
- Maintenance work ongoing.
- All FD Staircase (Entrance) completed.
- 3- Angel coming up.
THANK YOU.