Phase 1 Report

APPENDIX

Picture showing the complete Roofing on Lot 15

Retaining wall by the Gatehouse.

Picture showing complete Rafter on Lot 4, 5, 6 and 7

Picture showing the complete Roofing on Lot 11

Basement Foundation on Lot 17

Picture showing All FD Staircase (Entrance) completed

FD – 9, 8, 7, 6, and 5 Soakaway block work and column completed.

Picture showing the Bridge.

Picture showing Stab reinforcement work on Lot 16.

Picture showing the Park

All rendering at the gatehouse – 95 % done.

Picture showing the Gatehouse.

WORK SUMMARY

LOT – 3:

  • Roofing – 100%

LOT – 4:

  • Bamboo scaffolding – 100%
  • Rafter – 100%

LOT – 5: 

  • Internal rendering – 85%
  • Copping – 100%
  • Rafter – 100%

LOT – 6:

  • Internal rendering – 95%
  • Copping formwork completed.
  • Rafter – 100%

LOT – 7:

  • Internal rendering – 95%
  • Rafter – 100%
  • PPR piping and waste dropping.

LOT – 8:

  • Roofed

 LOT – 11:                                                                                                                                                                                                                                      

  • Copping – 100%
  • Internal rendering – 90%
  • Roofed

LOT – 12:

  • Internal rendering – 95%
  • Copping – 100%
  • Roof trusses – 95%

LOT – 13

  • Copping – 100%
  • Internal rendering – 95%

 

LOT – 14:

  • External rendering – 100%
  • Internal rendering – 95%
  • Screeding – 100%
  • Copping – 100%
  • Roof trusses – 20%

LOT – 15

  • Copping – 100%
  • Internal rendering – 70%

 

LOT – 16:

  • Slab formwork completed.
  • Reinforcement – 90%
  • Basement plastered.

LOT – 17:

  • Basement stepdown 1 Backfilled.
  • Blockwork at 80% on stepdown 2.

 

FD – 9, 8, 7, 6, and 5: Soakaway block work and column completed

            GATEHOUSE:

  • Wall tiled.
  • Maintenance work ongoing.

 

RETAINING WALL:

  • By the River ongoing.
  • By the Gatehouse – 85%
  • By the bridge to F-D 1 ongoing.

GENERAL WORKS

  • FD – 9 , 8, 7, 6, and 5: Soakaway block work and column completed.
  • Maintenance work ongoing.
  • All FD Staircase (Entrance) completed.
  • 3- Angel coming up.

                                                     THANK YOU.