APPENDIX

Fixing/installation of windows 100% done on Block A

 

Picture showing complete Roofing on Block B

 

Picture showing complete Roofing on Block C

 

Plastering of External wall 100% done on Block D

 

Picture showing the complete fixing of windows on Block E

BLOCK A

  • Fixing of electrical cables (Wiring) – 60% done.
  • Installation of Pop (Polysterene) Ceiling – 25%. Done.
  • Fixing/installation of windows – 100% done.
  • Window dressings and fixing of Window grooves – 50% done.
  • External wall screeding – in view.

BLOCK B

  • Electrical Piping down on each floor – 100% done.
  • Fixing of electrical cables (Wiring) – 60% done.
  • Plumbing work on each floor – 100% done.
  • Plastering of internal wall – 80% done.
  • Plastering of external wall – 100% done.
  • Fixing of wall skirtings and grooves – 90% done.
  • Installation of POP (polysterene) Ceiling – 20% done.
  • Fixing/installation of windows – 20% done.
  • External wall screeding – in view.

BLOCK C

  • Roofing (Step tiles installation) – 100% done.
  • Electrical Piping down on each floor – 100% done.
  • Plastering of internal wall – 90% done.
  • Plastering of external wall – 95% done.
  • Plumbing works on each floor – 100% done.
  • Fixing of wall skirting’s and grooves – 30% done.
  • Fixing of windows – in view

BLOCK D

  • Electrical piping down on each floor – 100% done.
  • Fixing of electrical cables (Wiring) – 60% done.
  • Installation of Pop ceiling – 40% done.
  • Plastering of external wall – 100% done.
  • Fixing/installation of windows – 100% done.
  • Window dressings and fixing of windows grooves – 60% done.
  • External wall screeding – in view.

BLOCK E

  • Electrical piping down on each floor – 100% done.
  • Plastering of internal wall – 70% done.
  • Plumbing works on each floor – 100% done.
  • Installation/Fixing of windows – 100% done.

SUMMARY OF STATE OF WORK

  • Plastering of internal wall 100% done on Block A.
  • Setting of partition wall 100% done on Block B
  • Roof trusses installation 100% done Block B.
  • Formwork and shuttering to third-floor slab 100% done on Block C.
  • Reinforcement to third-floor slab 100% done on Block C.
  • Plumbing works on each floor 100% done on Block D.
  • Roofing (step tiles installation) 100% done on Block E.

                                                                                                                THANK YOU.