APPENDIX
BLOCK A
- Fixing of electrical cables (Wiring) – 60% done.
- Installation of Pop (Polysterene) Ceiling – 25%. Done.
- Fixing/installation of windows – 100% done.
- Window dressings and fixing of Window grooves – 50% done.
- External wall screeding – in view.
BLOCK B
- Electrical Piping down on each floor – 100% done.
- Fixing of electrical cables (Wiring) – 60% done.
- Plumbing work on each floor – 100% done.
- Plastering of internal wall – 80% done.
- Plastering of external wall – 100% done.
- Fixing of wall skirtings and grooves – 90% done.
- Installation of POP (polysterene) Ceiling – 20% done.
- Fixing/installation of windows – 20% done.
- External wall screeding – in view.
BLOCK C
- Roofing (Step tiles installation) – 100% done.
- Electrical Piping down on each floor – 100% done.
- Plastering of internal wall – 90% done.
- Plastering of external wall – 95% done.
- Plumbing works on each floor – 100% done.
- Fixing of wall skirting’s and grooves – 30% done.
- Fixing of windows – in view
BLOCK D
- Electrical piping down on each floor – 100% done.
- Fixing of electrical cables (Wiring) – 60% done.
- Installation of Pop ceiling – 40% done.
- Plastering of external wall – 100% done.
- Fixing/installation of windows – 100% done.
- Window dressings and fixing of windows grooves – 60% done.
- External wall screeding – in view.
BLOCK E
- Electrical piping down on each floor – 100% done.
- Plastering of internal wall – 70% done.
- Plumbing works on each floor – 100% done.
- Installation/Fixing of windows – 100% done.
SUMMARY OF STATE OF WORK
- Plastering of internal wall 100% done on Block A.
- Setting of partition wall 100% done on Block B
- Roof trusses installation 100% done Block B.
- Formwork and shuttering to third-floor slab 100% done on Block C.
- Reinforcement to third-floor slab 100% done on Block C.
- Plumbing works on each floor 100% done on Block D.
- Roofing (step tiles installation) 100% done on Block E.