APPENDIX

Block A – Plastering of Parapet walls and Dressing of coping – 80% Done

 

Block B – Blockwork above Roof Beam – In progress.

 

Block C- Parapet Blockwork– 100% Done.

 

Block D- Casting of Roof Beam – 80% Done.

 

WORK PROGRESS

Block A.

  • General electrical pipping work – 90%
  • General Plumbing work – 90%
  • General internal plaster at A1-90%, A2 -90%, A3 -85%, A4 -90%, A5 -90%
  • General external plaster– 90%
  • Parapet Blockwork – 100%
  • Casting of coping – 100%
  • Plastering of Parapet walls and Dressing of coping – 80%
  • Internal Blockwork to Roof level – In progress.

Block B.

  • Casting of Roof Beam – 100%
  • General Electrical work – 70%
  • General plumbing work – 70%
  • General Internal plastering – B1-65%, B2-0%, B3-55%, B4-50%, B5-45%
  • Blockwork above Roof Beam – In progress.
  • Columns Extension – 100%

Block C.

  • General Electrical Piping work – 90%
  • General Plumbing work – 95%
  • General Internal plastering – C1-85%, C2-95%, C3-90%, C4-85%, C5-85%
  • General External plastering – 80%
  • Parapet Blockwork – 100%
  • Casting of coping – 100%
  • Plastering of parapet walls and Dressing of coping – 90%
  • Internal Blockwork to Roof level – In progress.

Block D.

  • Casting of Roof Beam – 80%
  • General Plumbing work – 55%
  • General Electrical work – 40%

 

 

                                                                                     THANK YOU.