Fixing/installation of windows 100% done on Block A.

External wall screeding – In view on Block B.

Fixing of wall skirting’s and Grooves -90% done on Block C.

Window dressings and fixing of window grooves 100% done on Block D.

External wall screeding – 10% done on Block E.

Picture showing the POP on Block D.

WORK SUMMARY

BLOCK A

  • Fixing of electrical cables (Wiring) –
  • Installation of Pop (Polysterene) Ceiling –
  • External wall screeding – 10% done.
  • External wall painting – In view.

BLOCK B

  • Fixing of Electrical cables (Wiring) –
  • Plastering of Internal wall – 90%
  • Fixing of wall skirtings and window Grooves – 100%
  • Installation of Pop (polysterene) Ceiling – 45%
  • Fixing/installation of windows – 80%
  • External wall screeding – In view.

BLOCK C

  • Fixing of wall skirting’s and Grooves – 90%
  • Window Dressings and fixing of window Grooves – 40%
  • Fixing of Electrical cables (wiring) – 60%
  • Installation of Pop (Polysterene) Ceiling – 20%
  • External wall screeding – In view.

BLOCK D

  • Fixing of electrical cables (Wiring) –
  • Installation of Pop (Polysterene) Ceiling – 75%
  • Window Dressings and fixing of windows Grooves – 100%
  • External wall screeding – 10% done.
  • External wall Painting – In

BLOCK E

  • Plastering of Internal wall – 100%
  • Window Dressings and Fixing of window Grooves – 100%
  • External wall screeding – 10%
  • Installation of POP Ceiling – In

SUMMARY OF STATE OF WORK

  • Plastering of internal wall 100% done on Block
  • Setting of partition wall 100% done on Block B
  • Roof trusses installation 100% done Block
  • Formwork and shuttering to third floor slab 100% done on Block
  • Reinforcement to third floor slab 100% done on Block
  • Plumbing works on each floor 100% done on Block
  • Roofing (step tiles installation) 100% done on Block