SITE ACTIVITY REPORT FOR THE MONTH OF SEPTEMBER 2021 (GLENDALE PEARL, ABUJA)

  APPENDIX Fixing/installation of windows 100% done on Block A   Picture showing complete Roofing on Block B   Picture showing complete Roofing on Block C   Plastering of External wall 100% done on Block D   Picture showing the complete fixing of windows on Block [...]

SITE ACTIVITY REPORT FOR THE MONTH OF AUGUST 2021 (CEDARWOOD CITY, ABUJA)

Phase 1 Report APPENDIX Picture showing the Screeding level on Lot 15   Retaining wall by the gatehouse.   Picture showing the Screeding level on Lot 14   LOT 11- Reinforcement work completed   Lot 12- Roof trusses – 95% done   Picture showing [...]

SITE ACTIVITY REPORT FOR THE MONTH OF AUGUST 2021 (COLOR CODE ESTATE, ABUJA)

APPENDIX Block A- Roof electrical pipe works - 40% done.   Block B – Block work to roof beam level - 100% done.   Block C- Roof slab cantilever reinforcements   Block D- Second-floor slab formwork -100% done   WORK PROGRESS Block A. General electrical pipping work [...]