SITE ACTIVITY REPORT FOR THE MONTH OF OCTOBER 2021 (GLENDALE PEARL, ABUJA)

APPENDIX Fixing/installation of windows 100% done on Block A.   Fixing/installation of windows 80% done on Block B.   Plastering of External wall 100% done on Block C.   Window dressings and fixing of window grooves 100% done on Block D.   Picture showing the complete [...]