SITE ACTIVITY REPORT FOR THE MONTH OF JUNE 2022, (GLENDALE POINT, ABUJA)
APPENDIX Block A - Casting of second floor slab completed. Block B - Forming of third floor slab completed WORK SUMMARYBLOCK ACasting of second floor slab completed.Removal of formwork completedBLOCK BForming of third floor slab completedBlock work on ground floor and first floor ongoing. [...]