SITE ACTIVITY REPORT FOR THE MONTH OF JULY 2022 (COLOR CODE EXTRA, ABUJA)

APPENDIX Block A - Formwork for first floor extension columns/lintels – 100% done. Block B - First floor block work – 100% done. Block C - Formwork for first floor slab, Beam and Staircase – 97% done. Block D - Reinforcements for second floor slab, beam [...]